• The U.S. Has Billions for Wind and Solar Projects. Good Luck Plugging T

    From Nimo@21:1/5 to All on Mon Feb 27 10:28:56 2023
    XPost: alt.engineering.electrical, alt.society.liberalism, sci.energy
    XPost: talk.politics.guns

    An explosion in proposed clean energy ventures has overwhelmed the system
    for connecting new power sources to homes and businesses.

    Plans to install 3,000 acres of solar panels in Kentucky and Virginia are delayed for years. Wind farms in Minnesota and North Dakota have been
    abruptly canceled. And programs to encourage Massachusetts and Maine
    residents to adopt solar power are faltering.

    The energy transition poised for takeoff in the United States amid record investment in wind, solar and other low-carbon technologies is facing a
    serious obstacle: The volume of projects has overwhelmed the nation’s antiquated systems to connect new sources of electricity to homes and businesses.

    So many projects are trying to squeeze through the approval process that
    delays can drag on for years, leaving some developers to throw up their
    hands and walk away.

    More than 8,100 energy projects — the vast majority of them wind, solar
    and batteries — were waiting for permission to connect to electric grids
    at the end of 2021, up from 5,600 the year before, jamming the system
    known as interconnection.

    That’s the process by which electricity generated by wind turbines or
    solar arrays is added to the grid — the network of power lines and
    transformers that moves electricity from the spot where it is created to
    cities and factories. There is no single grid; the United States has
    dozens of electric networks, each overseen by a different authority.

    PJM Interconnection, which operates the nation’s largest regional grid, stretching from Illinois to New Jersey, has been so inundated by
    connection requests that last year it announced a freeze on new
    applications until 2026, so that it can work through a backlog of
    thousands of proposals, mostly for renewable energy.

    It now takes roughly four years, on average, for developers to get
    approval, double the time it took a decade ago.

    And when companies finally get their projects reviewed, they often face
    another hurdle: the local grid is at capacity, and they are required to
    spend much more than they planned for new transmission lines and other upgrades.

    Many give up. Fewer than one-fifth of solar and wind proposals actually
    make it through the so-called interconnection queue, according to research
    from Lawrence Berkeley National Laboratory.

    “From our perspective, the interconnection process has become the No. 1
    project killer,” said Piper Miller, vice president of market development
    at Pine Gate Renewables, a major solar power and battery developer.

    After years of breakneck growth, large-scale solar, wind and battery installations in the United States fell 16 percent in 2022, according to
    the American Clean Power Association, a trade group. It blamed supply
    chain problems but also lengthy delays connecting projects to the grid.

    Electricity production generates roughly one-quarter of the greenhouse
    gases produced by the United States; cleaning it up is key to President
    Biden’s plan to fight global warming. The landmark climate bill he signed
    last year provides $370 billion in subsidies to help make low-carbon
    energy technologies — like wind, solar, nuclear or batteries — cheaper
    than fossil fuels.

    But the law does little to address many practical barriers to building
    clean energy projects, such as permitting holdups, local opposition or transmission constraints. Unless those obstacles get resolved, experts
    say, there’s a risk that billions in federal subsidies won’t translate
    into the deep emissions cuts envisioned by lawmakers.

    “It doesn’t matter how cheap the clean energy is,” said Spencer Nelson, managing director of research at ClearPath Foundation, an energy-focused nonprofit. “If developers can’t get through the interconnection process
    quickly enough and get enough steel in the ground, we won’t hit our
    climate change goals.”

    Waiting in line for years
    In the largest grids, such as those in the Midwest or Mid-Atlantic, a
    regional operator manages the byzantine flow of electricity from hundreds
    of different power plants through thousands of miles of transmission lines
    and into millions of homes.

    Before a developer can build a power plant, the local grid operator must
    make sure the project won’t cause disruptions — if, for instance, existing power lines get more electricity than they can handle, they could overheat
    and fail. After conducting a detailed study, the grid operator might
    require upgrades, such as a line connecting the new plant to a nearby substation. The developer usually bears this cost. Then the operator moves
    on to study the next project in the queue.

    This process was fairly routine when energy companies were building a few
    large coal or gas plants each year. But it has broken down as the number
    of wind, solar and battery projects has risen sharply over the past
    decade, driven by falling costs, state clean-energy mandates and, now,
    hefty federal subsidies.

    “The biggest challenge is just the sheer volume of projects,” said Ken
    Seiler, who leads system planning at PJM Interconnection. “There are only
    so many power engineers out there who can do the sophisticated studies we
    need to do to ensure the system stays reliable, and everyone else is
    trying to hire them, too.”

    PJM, the grid operator, now has 2,700 energy projects under study — mostly wind, solar and batteries — a number that has tripled in just three years.
    Wait times can now reach four years or more, which prompted PJM last year
    to pause new reviews and overhaul its processes.

    Delays can upend the business models of renewable energy developers. As
    time ticks by, rising materials costs can erode a project’s viability.
    Options to buy land expire. Potential customers lose interest.

    Two years ago, Silicon Ranch, a solar power developer, applied to PJM for permission to connect three 100-megawatt solar projects in Kentucky and Virginia, enough to power tens of thousands of homes. The company, which
    often pairs its solar arrays with sheep grazing, had negotiated purchase options with local landowners for thousands of acres of farmland.

    Today, that land is sitting empty. Silicon Ranch hasn’t received feedback
    from PJM and now estimates it may not be able to bring those solar farms
    online until 2028 or 2029. That creates headaches: The company may have to decide whether to buy the land before it even knows whether its solar
    arrays will be approved.

    “It’s frustrating,” said Reagan Farr, the chief executive of Silicon
    Ranch. “We always talk about how important it is for our industry to
    establish trust and credibility with local communities. But if you come in
    and say you’re going to invest, and then nothing happens for years, it’s
    not an optimal situation.”

    PJM soon plans to speed up its queues — for instance, by studying projects
    in clusters rather than one at a time — but needs to clear its backlog
    first.

    ‘Imagine if we paid for highways this way’
    A potentially bigger problem for solar and wind is that, in many places
    around the country, the local grid is clogged, unable to absorb more
    power.

    That means if a developer wants to build a new wind farm, it might have to
    pay not just for a simple connecting line, but also for deeper grid
    upgrades elsewhere. One planned wind farm in North Dakota, for example,
    was asked to pay for multimillion-dollar upgrades to transmission lines hundreds of miles away in Nebraska and Missouri.

    These costs can be unpredictable. In 2018, EDP North America, a renewable energy developer, proposed a 100-megawatt wind farm in southwestern
    Minnesota, estimating it would have to spend $10 million connecting to the grid. But after the grid operator completed its analysis, EDP learned the upgrades would cost $80 million. It canceled the project.

    That creates a new problem: When a proposed energy project drops out of
    the queue, the grid operator often has to redo studies for other pending projects and shift costs to other developers, which can trigger more cancellations and delays.

    It also creates perverse incentives, experts said. Some developers will
    submit multiple proposals for wind and solar farms at different locations without intending to build them all. Instead, they hope that one of their proposals will come after another developer who has to pay for major
    network upgrades. The rise of this sort of speculative bidding has further jammed up the queue.

    “Imagine if we paid for highways this way,” said Rob Gramlich, president
    of the consulting group Grid Strategies. “If a highway is fully congested,
    the next car that gets on has to pay for a whole lane expansion. When that driver sees the bill, they drop off. Or, if they do pay for it themselves, everyone else gets to use that infrastructure. It doesn’t make any sense.”

    A better approach, Mr. Gramlich said, would be for grid operators to plan transmission upgrades that are broadly beneficial and spread the costs
    among a wider set of energy providers and users, rather than having
    individual developers fix the grid bit by bit, through a chaotic process.

    There is precedent for that idea. In the 2000s, Texas officials saw that existing power lines wouldn’t be able to handle the growing number of wind turbines being built in the blustery plains of West Texas and planned
    billions of dollars in upgrades. Texas now leads the nation in wind power. Similarly, MISO, a grid spanning 15 states in the Midwest, recently
    approved $10.3 billion in new power lines, partly because officials could
    see that many of its states had set ambitious renewable energy goals and
    would need more transmission.

    But this sort of proactive planning is rare, since utilities, state
    officials and businesses often argue fiercely over whether new lines are necessary — and who should bear the cost.

    “The hardest part isn’t the engineering, it’s figuring out who’s going to
    pay for it,” said Aubrey Johnson, vice president of system planning at
    MISO.

    Climate goals at risk
    As grid delays pile up, regulators have taken notice. Last year, the
    Federal Energy Regulatory Commission proposed two major reforms to
    streamline interconnection queues and encourage grid operators to do more long-term planning.

    The fate of these rules is unclear, however. In December, Richard Glick,
    the former regulatory commission chairman who spearheaded both reforms,
    stepped down after clashing with Senator Joe Manchin III, Democrat of West Virginia, over unrelated policies around natural gas pipelines. The
    commission is now split between two Democrats and two Republicans; any new reforms need majority approval.

    If the United States can’t fix its grid problems, it could struggle to
    tackle climate change. Researchers at the Princeton-led REPEAT project
    recently estimated that new federal subsidies for clean energy could cut electricity emissions in half by 2030. But that assumes transmission
    capacity expands twice as fast over the next decade. If that doesn’t
    happen, the researchers found, emissions could actually increase as solar
    and wind get stymied and existing gas and coal plants run more often to
    power electric cars.

    Massachusetts and Maine offer a warning, said David Gahl, executive
    director of the Solar and Storage Industries Institute. In both states, lawmakers offered hefty incentives for small-scale solar installations. Investors poured money in, but within months, grid managers were
    overwhelmed, delaying hundreds of projects.

    “There’s a lesson there,” Mr. Gahl said. “You can pass big, ambitious
    climate laws, but if you don’t pay attention to details like
    interconnection rules, you can quickly run into trouble.”

    Brad Plumer is a climate reporter specializing in policy and technology
    efforts to cut carbon dioxide emissions. At The Times, he has also covered international climate talks and the changing energy landscape in the
    United States. @bradplumer

    A version of this article appears in print on Feb. 24, 2023, Section A,
    Page 1 of the New York edition with the headline: U.S. Solar Goal Stalled
    by Wait On Creaky Grid. Order Reprints | Today’s Paper | Subscribe

    <https://www.nytimes.com/2023/02/23/climate/renewable-energy-us- electrical-grid.html>

    --- SoupGate-Win32 v1.05
    * Origin: fsxNet Usenet Gateway (21:1/5)