Use of buster-security will pass from the Security Team to LTS in a few
days time, so we should get the EOL point release organised. We need at
least a couple of weeks to get things sorted, so as some suggestions:
- August 20
- [August 27 doesn't work for at least me and the Images Team, so nope]
- September 3rd
- September 10th
We're currently only 3 weeks past the 11.4 bullseye point release, but
that was also about 6 weeks late. It's therefore worth considering
whether we want to try and get 11.5 out sooner and get back onto the
previous track, or delay it a little more and aim for every two months
from 11.4's release date.
tl;dr - please indicate your availability / preferences for the above
dates (for both 10.13 and 11.5) and any opinions on whether we should
do them at the same time or separately.
Hi,
Use of buster-security will pass from the Security Team to LTS in a few
days time, so we should get the EOL point release organised. We need at
least a couple of weeks to get things sorted, so as some suggestions:
- August 20
- [August 27 doesn't work for at least me and the Images Team, so nope]
- September 3rd
- September 10th
We're currently only 3 weeks past the 11.4 bullseye point release, but
that was also about 6 weeks late. It's therefore worth considering
whether we want to try and get 11.5 out sooner and get back onto the
previous track, or delay it a little more and aim for every two months
from 11.4's release date.
tl;dr - please indicate your availability / preferences for the above
dates (for both 10.13 and 11.5) and any opinions on whether we should
do them at the same time or separately.
Thanks,
Adam
Use of buster-security will pass from the Security Team to LTS in a few
days time, so we should get the EOL point release organised. We need at
least a couple of weeks to get things sorted, so as some suggestions:
- August 20
- [August 27 doesn't work for at least me and the Images Team, so nope]
- September 3rd
- September 10th
We're currently only 3 weeks past the 11.4 bullseye point release, but
that was also about 6 weeks late. It's therefore worth considering
whether we want to try and get 11.5 out sooner and get back onto the
previous track, or delay it a little more and aim for every two months
from 11.4's release date.
tl;dr - please indicate your availability / preferences for the above
dates (for both 10.13 and 11.5) and any opinions on whether we should
do them at the same time or separately.
- August 20
- [August 27 doesn't work for at least me and the Images Team, so nope]
- September 3rd
- September 10th
any opinions on whether we should do them at the same time or
separately.
Hi,
On Thu, 2022-07-28 at 17:09 +0100, Adam D. Barratt wrote:
- August 20
- [August 27 doesn't work for at least me and the Images Team, so nope]
- September 3rd
- September 10th
All dates should still work for me.
any opinions on whether we should do them at the same time or
separately.
Either is fine with me.
Ansgar
Use of buster-security will pass from the Security Team to LTS in a[...]
few
days time, so we should get the EOL point release organised. We need
at
least a couple of weeks to get things sorted, so as some suggestions:
- August 20
- [August 27 doesn't work for at least me and the Images Team, so
nope]
- September 3rd
- September 10th
tl;dr - please indicate your availability / preferences for the above
dates (for both 10.13 and 11.5) and any opinions on whether we should
do them at the same time or separately.
Hi,
On Thu, 2022-07-28 at 17:09 +0100, Adam D. Barratt wrote:
- August 20
- [August 27 doesn't work for at least me and the Images Team, so nope]
- September 3rd
- September 10th
All dates should still work for me.
any opinions on whether we should do them at the same time or
separately.
Either is fine with me.
Ansgar
Sysop: | Keyop |
---|---|
Location: | Huddersfield, West Yorkshire, UK |
Users: | 300 |
Nodes: | 16 (2 / 14) |
Uptime: | 56:01:31 |
Calls: | 6,712 |
Files: | 12,243 |
Messages: | 5,355,474 |